Passau's new bridge: City Councilor Putzke criticizes crooked architecture!

Passau's new bridge: City Councilor Putzke criticizes crooked architecture!
Passau, Deutschland - In Passau there is again conversation! Holm Putzke, a frameworkless CSU city council, draws attention to the new Poststeg at the main train station with a critical view of the new Poststeg. In particular, he criticizes that the bridge is wrong. On his tour he broadcast greetings from the construction site and compared the situation with a “Pisa Gag”, while he described the bridge construction work as a “bitter reality” in the cityscape. In the background the old pedestrian bridge could be seen, which appears far less wrong. Apparently you need a good hand for the architecture that the city urgently needs.
like the Passauer Neue Presse reported, the construction project of Deutsche Post AG began on June 14, 2024 with the demolition of the existing mail. At this point there is now a new pedestrian bridge that will be positioned about 10 to 15 meters west of the old platform. This new connection between Grünaustraße in the south and Bahnhofstrasse in the north plays a central role in the connection to the central omnibus station and contributes to improving traffic safety.
construction time and traffic impairments
The new building was plannedafter building investigations had shown that the old post platform was in an insufficient state, which impaired stability and traffic safety. Therefore, it was decided to rebuild the bridge completely. The Committee for Urban Development and Mobility had already approved the proposal of the Deutsche Post DHL Group for the replacement for replacement construction in April 2023. After completion, the city of Passau will take over the bridge and is then also responsible for traffic safety.
The construction work is divided into five sections, whereby from April 14 to May 9, 2025, traffic impairments in Oberen Bahnhofstrasse and Grünaustraße are expected. During this time, the P5 parking lot between house numbers 25 and 29a is completely blocked. The alternative parking spaces for taxis and short-term parkers are temporarily shown on Bahnhofstrasse.
The construction phases in detail
For everyone who wants to be well informed about the progress, here is an overview of the construction phases:
date Th>
| ||
---|---|---|
First section | 14.04. - 04/21/2025 | Preparations of the crane space for caterpillar crane. |
Second section | 04.04. - 30.04.2025 | structure of the caterpillar crane; Complete blocking of the upper Bahnhofstrasse. |
third section | 01.05. - 04.05.2025 | Einhub of the pedestrian bridge; Full closure of the upper Bahnhofstrasse. |
fourth section | 05.05. - 09.05.2025 | dismantling of the caterpillar crane; Railway available via secure pedestrian tour. |
construction phase Grünaustraße | 01.05. - 06.05.2025 | Einhub of the pedestrian bridge; Complete blocking of the Grünaustraße. |
The new construction work is another sign of development in the city, but with critical voices like that of Putzke it remains to be seen whether Passau can soon look forward to a straight and reliable poststeg. What is certain is that the construction is an important chapter for improving the infrastructure in the city. While some are upset about the challenges, others may soon see the positive changes in the cityscape.